Key dates

M1 - Roadmap Initial Release

Created v1 in 2 days for internal feedback and communications.

Done
Mar 29, 2026Jul 30, 2026123 days

M2 - Initiatives Inclusion

Include initiatives and capx budget codes heirarchy per @Nikkita Willis and @Travis Barrs

Done
Jul 22, 2026Jul 23, 20261 days

M3 - Feedback Redesign

Complete design overhaul to stay attuned to evolving project reqs.

Done
Jul 24, 2026Jul 27, 20263 days

M4 - Jira Integration

Integration of JIRA epics at the project level. First pass. More to come.

Done
Jul 28, 2026Jul 29, 20261 days

M5 - Adoption and communication

Tentatively use in Q4 to complement PI Planning (led by @Nikkita Willis). Dates TBD.