Roadmap
Customer Facing

DE Home / Platform EFP

Key dates

Initial Prototype

Done
Feb 23, 2026Mar 1, 20266 days

Chat AI & Feature Parity

Done
Mar 5, 2026Apr 9, 202635 days

Internal Feedback Loop

Done
Apr 1, 2026Apr 30, 202629 days

M2 - Legacy platform — dev

Opt-in banner/workflow, user opt-in setting, and global nav changes (§4.5) built on the legacy platform.

Jul 29, 2026Aug 12, 202614 days

M3 - DE Home page & feature hardening

Jul 30, 2026Aug 19, 202620 days

M4 - Audit resolution

Every Audit-flagged item (Classrooms/Assignments, Assign, Profile → Recent Activity/History, Release Notes) has a real-vs-faked determination and a decision recorded against §11.

Jul 31, 2026Aug 12, 202612 days

M5 - Legacy platform — QA

QA and regression complete on the §4.5 legacy platform changes; no open blocking defects.

Aug 13, 2026Aug 26, 202613 days

M6 - Full-coverage testing

Unit, integration, E2E, accessibility, performance, and regression coverage per §6 complete across rad-helix and rad-platform-layer.

Aug 13, 2026Aug 26, 202613 days

M7 - Legacy platform — release

Opt-in banner, user setting, and nav changes shipped to production ahead of go-live.

Aug 27, 2026Aug 28, 20261 days

M8 - Full capability parity / go-live readiness

All P1 must-haves at Built; go/no-go checkpoint for Aug 30 launch.

Aug 28, 2026Aug 29, 20261 days

M9 - Phase 1 launch — teacher opt-in live

LIMITED - teacher opt-in testing available; capability to activate for a small subset of users the same day.

Aug 28, 2026Aug 31, 20263 days

M10 - Phase 1 iteration window

Refinements and fixes shipped based on telemetry, Pulse feedback, and further QA from the initial opt-in cohort.

Aug 31, 2026Sep 28, 202628 days

M11 - Phase 2 expansion

Opt-in expanded to the Phase 2 cap

Sep 28, 2026Sep 29, 20261 days

M12 - Phase 2 iteration window

Refinements and fixes shipped based on Phase 2 cohort feedback and QA.

Sep 30, 2026Oct 28, 202628 days

M13 - Phase 3 expansion

Opt-in expanded to the Phase 3 cap; scale/performance validation per §6 confirmed ahead of the 20x jump.

Oct 28, 2026Oct 29, 20261 days

M14 - Phase 3 iteration window

Refinements and fixes shipped based on Phase 3 cohort feedback and QA.

Oct 30, 2026Nov 20, 202621 days

M15 - Phase 4 expansion

Opt-in expanded to the Phase 4 cap — final expansion within this plan's window.

Nov 20, 2026Nov 23, 20263 days